Major City Construction on Adelaide St W (Bathurst St to Parliament St)

Please be advised that City construction work on Adelaide Street is commencing. Construction on the Ontario Line will require a prolonged road closure on Queen Street West (St. James Street to Yonge Street). As a result, the 501 Queen streetcar will be diverted to Adelaide Street (eastbound) and Richmond Street (westbound). In an effort to prepare for the diversion, the City will replace the 100 year old watermain on Adelaide Street (York Street to Victoria Street). At the same time, the ageing streetcar tracks on Adelaide Street (Charlotte Street to York Street) will be replaced (in some sections reinstated) to create additional TTC route diversion in the downtown core.

Traffic Updates: In addition, the City is taking this opportunity to improve safety for road users on Adelaide Street by relocating the existing cycle track from the south side to the north side of the street from Bathurst Street to Parliament Street. The City will also modify traffic signal timing, install new bike signals and pedestrian safety improvements at various locations on the same section of Adelaide Street.

Please note that when the contractor begins construction work in earnest, Adelaide Street will be reduced up to a single eastbound lane from Spadina Avenue to Victoria Street. People driving and cycling will be required to share the travel lane – single file.

Learn more about the planned travel restrictions and work phases for the entire project under the ‘Construction Map’ accordion.

Start Date: September 2022 – Anticipated December 2022 | *Timeline is subject to change


Construction Update #9

Portions of the sidewalk will be dug up, impeding pedestrian traffic.

The City’s contractor is nearing completion with Phase 2 track reinstatement, from west of Duncan Street towards Widmer Street.  Current estimates suggest that the contractor will complete this phase by early December.

Since construction work is progressing very well, work on Phase 3 (Widmer Street to Charlotte Street) is expected to start the week of December 5 (next week).

Crews have replaced the watermain from York Street towards Bay Street (Phase 1A), and are now replacing the water service connections on the north side of Adelaide Street. The contractor is in the process of confirming underground utility locates from Victoria Street towards Bay Street before the excavation process begins. From this point, excavation is expected to begin the week of December 12.

We sincerely appreciate your patience and understanding during this time especially with the ongoing traffic delays, noise, dust and vibration associated with this project.

The City’s contractor is making excellent progress with Phase 2 track reinstatement, from west of Duncan Street towards east of Peter Street, with work being more than half completed.  Current estimates suggest that the contractor will complete the work by early December.

Since construction work is progressing very well, the contractor is aiming to begin work on Phase 3 (Widmer Street to Charlotte Street) in early December.

Watermain replacement work is progressing well on York Street towards Bay Street (Phase 1A). In mid December, the contractor is anticipating beginning the watermain replacement work on Bay Street towards Victoria Street.

We sincerely appreciate your patience and understanding during this time especially with the ongoing traffic delays, noise, dust and vibration associated with this project.

LEGEND
Watermain replacement: Phase 1A, York Street to Victoria Street
Streetcar track reinstatement: Phase 1B to Phase 3, Spadina Avenue to York Street
Pavement marking: Phase 4, Bathurst Street to Parliament Street

Watermain Replacement

  • Phase 1A: Crews will work between east of York Street and Bay Street: October 24
    • Upon completion of the York Street to Bay Street section, crews will work between Bay Street and Victoria Street

Streetcar Track Reinstatement 

  • Phase 1B: Crews will start at York Street and work westward towards University Avenue: October 24
    • Crews will work at the University Avenue and Adelaide Street intersection: October 27
    • Crews will start at University Avenue and work westward towards Duncan Street upon completion of the intersection work
  • Phase 2: Crews will start at Duncan Street and work westward towards Widmer Street: November 7
  • Phase 3: Crews will start at Widmer Street and work westward towards Charlotte Street. This work can only proceed once phase 1B is completed
  • Phase 4: Upon completion of phase 1A to phase 3, crews will undertake pavement marking work, and will relocate the Adelaide Street cycle track to the north side of the street

Travel impacts

Adelaide Street 

  • Lanes continue to be reduced to a single eastbound lane through the active work areas.
    • People cycling can share the single lane with people driving.
    • The Adelaide Cycle Track continues to be operational east and west of the work areas.

Intersections

  • Travel lanes on University Avenue on approach to Adelaide Street are now open in each direction.
  • There will be partial intersection closures on Adelaide Street at the following intersecting points:
    • John Street
    • Widmer Street
    • Duncan Street

Sidewalks

  • In the event that sidewalk work is required, a safe and clearly signed (alternate) pedestrian access will be provided.

Please pay close attention to posted signage when traveling in the area. Please pay close attention to posted signage when traveling in the area.

Virtual trailer drop-ins
The project team will host bi-weekly virtual trailer drop-in meetings where anyone can drop-in virtually and ask questions about the Adelaide Street Construction project.

Public Consultation Unit staff, the Project Manager, and TTC Senior Community Liaison will be present to answer questions.

When? Bi-weekly, starting on Monday, August 29, 2022, from 10:00 a.m. to 11:00 a.m.
Where? Login directly, or call: 416-915-6530 and enter access code 2453 698 0265

CONTACT:
By phone: 416-392-0472
By email: adelaideconstruction@toronto.ca

Visit the project webpage: toronto.ca/AdelaideConstruction


For more details and resources, please see below:

 CONTACT:

Dedicated email:  adelaideconstruction@toronto.ca

Or contact: Michael Vieira | Senior Public Consultation Coordinator | (416) 392-0472 | Michael.Vieira3@toronto.ca